Hilton Birmingham Metropole - NEC, Birmingham

 - Click to enlarge

Client:

Hilton International

Project:

Replacement of existing "Individual AC" units with 4 Pipe FCU system to Main Bedroom Blocks (530 Bed) Provision of Cool-Fire Installation. Major Lift renewal works. Sub-mains renewal to Bedrooms. Provision of New Chillers.

Service Value:

£10.15m

Project Programme:

June 2004 - due for completion 2008

M&E Services:

  • Installation of 4 Pipe "Cool-Fire" System combining Chiller Water & Sprinkler Systems.
  • New Chillers & Associated Distribution.
  • Integration with Existing MPHW & Chilled Water Infrastructure.
  • Upgrade & Enhancements to the site BMS Infrastructure.
  • New Sprinklers to all Public / Function / BOH Areas.
  • New Sub-Mains Installation serving Metropole & Warwick Bedroom Wings (680 Bedrooms).
  • New Transformers.
  • HV Mains Modifications.
  • Refurbishment of all Guest & Goods Lifts.
Website designed by BSolve IT Limited
Accredited Search Engine Optimisation, and Search Engine Submission Professionals
Valid HTML 4.01 Transitional Valid CSS Level Triple-A conformance icon, W3C-WAI Web Content Accessibility Guidelines 1.0

read more »