Arcadia Distribution Centre, Redmoor, Milton Keynes
Client:
Burton Group PLC
Architects:
Geoffrey Reid & Partners (Phase 1) / Simons Construction (Phase 2)
Project:
Extensions to the existing Distribution Centre Warehouse consisting of 3 floor levels - total area of 19,000m2
Service Value:
Phase 2 - £1.25m
Project Programme:
Phase 1 - 65 weeks (Costain Construction) / Phase 2 - 32 weeks (Simons Construction) Completed Autumn 2003
M&E Services:
Distribution Centre Warehouse
- New Centralised Indirect Gas Fired Ducted Heating & Ventilation System.
- Extension of the Existing Sprinkler Protection System.
- Smoke Ventilation System.
- Electrical Distribution / Automatic Conveyor System.
- Fire Alarm System.
- Lighting / Emergency Lighting.
- Security Systems, Door Monitoring, CCTV.
Transport Offices, Refurbishment of Existing Staff Offices
- New Ventilation System / Kitchen Extract System / Hood.
- Comfort Cooling using Split A/C Units.
- Domestic Hot / Cold Water, Sanitary Plumbing & Gas Distribution.
- New Lighting.
- Fire Alarm Modifications.
- Small Power & Kitchen Equipment.
- Security Modifications.
Below Ground Services
- Major Below Ground Service modifications, including Gas, Domestic Water Mains, Fire Hydrant Mains & Electrical Distribution Mains.